JHT 2009-2011 Project Schedule
- 3 August 2009: Projects begin
- 1 February 2010: Semi-annual reports due.
- 1-4 March 2010: PI makes presentation at the IHC and possibly meets with TPC/NHC points of contact.
- 1 April 2010: Year two renewal proposal due.
- 1 June 2010: PIs make preparations for and begin real-time testing and evaluation during 2010 hurricane season.
- June 2010: Second year of funded activity for renewed projects begins.
- 3 August 2010: Year-one annual progress reports due.
- 28 February 2011: Semi-annual year two report projects due.
- March 2011: PI makes presentation at the IHC and possibly meets with TPC/NHC points of contact.
- 3 August 2011: Final reports due.
- December 2011: Decision on operational implementation of the all projects by the TPC Director.
|